Key Takeaways
- Who: Every Tennessee city, county, metropolitan government, and planning commission that reviews development applications, starting January 1, 2027.
- What: HB 2552 (Public Chapter 1044) sets 30- and 60-business-day deadlines for reviewing site plans, plats, other development applications, and site inspections. It caps deficiency notices at two per application, and a missed review deadline means automatic approval. Where there’s a formal development contract, towns also have 120 business days after a developer-hired engineer certifies the work to either release the surety or place it on a planning commission or governing body agenda.
- Benefit: Citywide Permitting tracks every deadline, warns staff before time runs out, and combines reviewer comments into one letter, so staff can meet each deadline without counting days by hand.
What is Tennessee Public Chapter 1044?
Starting on January 1, 2027, Tennessee Public Chapter 1044 puts strict development review deadlines on every city, county, and planning commission in the state. If a town misses one, the application is approved automatically, even if it has problems.
The law began as House Bill 2552 (HB2552). Governor Bill Lee signed it into law on May 22, 2026, and it was assigned Public Chapter 1044 on May 27. It sets the first statewide mandatory deadlines for local review of development applications in Tennessee (MTAS PC 1044 FAQ).
The law reaches across the whole development process:
- preliminary plats and concept plans
- site and development plans
- construction plans for roads and drainage
- land disturbance permits
- related site inspections
PC 1044 doesn’t require towns to approve bad projects. It requires them to be organized, fast, and thorough the first time. For many planning, engineering, and public works departments, meeting the new development review deadlines means rethinking how applications move from desk to desk.
The law is meant to streamline development review. According to the UT Center for Local Planning, its main objective is to make sure plans are either approved by staff or sent quickly to the decision-making body. For towns, faster review can also mean projects that break ground sooner and new development that reaches the tax rolls sooner.
What PC 1044 doesn’t cover
The law does not apply to:
- building, fire, plumbing, mechanical, or electrical permits and inspections, which follow separate state timelines
- rezonings and other legislative actions
- state agencies, and utility districts that operate independently of local governments
- projects the town funds itself, such as public roads and parks
- contracts already in place on December 31, 2026
The existing 60-day rules for final subdivision plats also still apply alongside PC 1044 (UT Center for Local Planning policy guide).
What are the PC 1044 deadlines?
Public Chapter 1044 comes down to four numbers: 30, 60, two, and 120. Here’s where each one applies.
| Deadline | What the town must do |
| 30 business days | Send the applicant written comments or a list of what’s missing |
| 60 business days | Approve the application or place it on a council or planning commission agenda |
| 30 business days after resubmittal | Approve the application or place it on an agenda once the applicant documents that every deficiency is fixed |
| 2 notices maximum | Send no more than two deficiency (“please fix this”) letters per application |
| Site inspections: 30 or 60 business days | Approve the inspection or send written deficiencies within 30 business days of the request. If it can’t be approved, place it on an agenda within 60. |
| 120 business days | Where there’s a formal development contract, either release the surety or place it on a planning commission or governing body agenda once a developer-hired engineer certifies the work is complete. Send written notice within 20 business days of any deficient work that justifies withholding release. |
These are business days, not calendar days. Weekends and holidays affect the count, and manual counting often gets it wrong.
The two-notice cap matters as much as the clocks. Reviewers have to catch problems the first time, because there may not be a third chance to ask.
What happens after the second notice?
If problems remain after the second deficiency notice, staff must do one of three things:
- deny the application and refund 50% of the fees
- approve it with conditions, if local regulations allow that
- place it on the next available planning commission or governing body agenda
If the applicant instead documents that every deficiency is fixed, a new 30-business-day clock starts. Within that window, staff must approve the application or put it on an agenda. Missing that deadline also means automatic approval.
Incomplete applications
Staff can reject an incomplete submittal in writing within 30 business days, and that rejection doesn’t count toward the two-notice limit. But the clocks run from submission, not acceptance, so completeness checks need to happen right away. Towns should define what counts as a “complete” application in their regulations.
The real risk of PC 1044: automatic approval
The UT Center for Local Planning is clear: if a town misses a PC 1044 deadline, the application is approved automatically, exactly as submitted.
In practice, that can mean substandard plans moving forward, roads and pipes the town later has to maintain, and liability the town never agreed to take on. One stalled file in one department can be enough.
The two-notice cap adds a financial risk too. If staff deny an application after the second notice, the town must refund half of the application fees.
The goal of the law isn’t to force approvals. It’s to make sure plans are either approved or sent to decision-makers quickly. Towns keep the authority to deny or condition projects. They just have to act on time.
Where current permitting processes will break under PC 1044
Most towns won’t miss deadlines because staff are slow. They’ll miss them because the process hides where each file is and how much time it has left.
Challenge 1: Tracking business days across many reviewers
A single application may pass through Planning, Engineering, Utilities, and Stormwater. A spreadsheet or a Friday status report can’t show that a file is on business day 26 of 30 while it sits untouched in one department.
Without real-time visibility, supervisors find out about a problem after the deadline has passed, when the application is already approved.
Challenge 2: The two-notice cap
When each department sends its own comments separately, a town can use up both deficiency notices on a single application before every reviewer has weighed in.
PC 1044 strongly encourages towns to combine every department’s comments into one document. With only two notices allowed, one complete letter is the safest approach, because anything a reviewer misses may not get a second chance.
Challenge 3: Surety release and the asset handoff
Today, an engineer’s certification often lands on one desk while the bond sits with finance. The new roads and pipes may never make it into the town’s asset records at all.
Where a town has a formal development contract, the developer can hire a licensed engineer to certify that the work is complete. The developer pays for that engineer, and the town can’t choose who it is. From there, the town has 120 business days to either release the surety or place it on a planning commission or governing body agenda. If it plans to withhold release, it must send written notice of the deficient work within 20 business days.
Challenge 4: Site inspections on their own clock
Development inspections such as subgrade, paving, utilities, and stormwater have their own 30- and 60-business-day deadlines. Inspection requests that arrive by phone or email are easy to lose track of, and a missed one carries the same automatic approval risk.
How Citywide Permitting helps Tennessee towns comply with PC 1044
Citywide Permitting gives Tennessee towns one platform to manage every development application from submission to approval, so meeting PC 1044 deadlines doesn’t depend on someone counting business days by hand. Every application is tracked through each review stage, and staff and supervisors are alerted before the 30- and 60-business-day deadlines run out, not after.
Automated routing and shared workflows give Planning, Engineering, and Utilities visibility into the same file. Reviewers’ comments are combined into a single deficiency letter, which helps towns stay within the two-notice limit. Applicants submit and track their files through the Citywide Customer Portal with email notifications, and processing-time reports show supervisors where applications are getting stuck.
6 questions to ask before PC 1044 takes effect in January
An honest look at your current process will show where PC 1044 is most likely to catch you. Start with these six questions.
- What is our true review time, in business days? Use real numbers from recent applications, not estimates.
- Where do files sit? Find the department or step where applications wait the longest.
- Who counts the clock? If someone is counting business days by hand, the process is fragile.
- How many comment letters do we send today? If each department sends its own, you could use up the two-notice limit on one application.
- What happens after an engineer certifies completion? Trace the path from certification to bond release to your asset records, and note every handoff.
- Have we defined a “complete” application? Rejecting an incomplete submittal doesn’t use up a deficiency notice, but the clock starts at submission. Put a clear completeness checklist in your regulations and check every submittal right away.
Get Started
January 1, 2027 is close, but there’s still time to audit your process and close the gaps before the first deadline arrives. Start with the six questions above.
If your answers point to manual tracking, scattered comments, or a slow handoff to finance, those are the places to fix first. They’re also where Citywide Permitting can help the most.
Book a discovery call with PSD Citywide